CITY OF FAIRFIELD • S146718-01

02NOV
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

08NOV
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

15NOV
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

17NOV
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

22NOV
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

29NOV
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

06DEC
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

27DEC
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

27DEC
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

29DEC
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

03JAN
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

03JAN
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

05JAN
Electrical
The wiring harness is installed. Emergency and scene lighting are mounted and terminated at the breaker panel.

10JAN
Electrical
The wiring harness is installed. Emergency and scene lighting are mounted and terminated at the breaker panel.

12JAN
Electrical
The wiring harness is installed. Emergency and scene lighting are mounted and terminated at the breaker panel.



26JAN
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


07FEB
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

14FEB
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.