ARLINGTON • S14654-01

03MAR
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

07MAR
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

09MAR
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

14MAR
Electrical
The wiring harness is installed. Emergency and scene lighting are mounted and terminated at the breaker panel.

17MAR
Electrical
The wiring harness is installed. Emergency and scene lighting are mounted and terminated at the breaker panel.




05APR
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


07APR
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


12APR
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

14APR
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

19APR
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

21APR
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

26APR
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

24MAY
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

26MAY
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.